Fire compliance complete, services in, reconfiguration underway. Where the Leeds supported-living project stands this month.
A short one, because the site is busy.
Done this month
- Fire doors, interlinked detection and emergency lighting installed and tested.
- New electrical installation certified. New heating system commissioned.
- Two oversized reception rooms reconfigured into four bedrooms with en-suites.
Next
Kitchens, flooring and decoration. Accessibility works to the ground-floor bathroom. Provider inspection is booked for the end of the programme.
Timing
The programme was estimated at twenty-six weeks. We are on week nineteen and on plan. If that changes, this page will say so.
"Progress recorded throughout, including the delays."